Bronte Construction was hired as a sub-contractor by Toronto Zeneith to complete a portion of the QEW East of Dixie Road to the East Mall Etobicoke Creek Bridge Project. Our scope of work consisted of the supply and installation of a Nosie Barrier System, Roadway Protection System, Various Pile which included: H-Pile, Auguring Pile, Caisson Piles.
Bronte Construction Deep Foundation division deployed a variety of different equipment to facilitate our scope which included a Soilmec SR65 for large diameter Bridge Caissons, HMC Side Grip Vibro for the installation of the Roadway Protection System, HD Engineering Crawler Rig for Tiebacks and a Excavator Mounted HTFB 60 Lodril for the Noise wall Footings.
Scope of Work
- Traffic Control
- Supply and installation of Concrete Secant Wall
- Design and Construction of Road Protection Shoring System
- Supply and installation of Tieback
- 1500 meters of Caissons
- 483 meters of H-Piles
- 448 meters of Auguring Piles
- Sheet Piling Works
- Concrete Works
- Site Restoration