Bronte Construction was hired to rehabilitate a private dam in Georgetown for Crozier & Associates Consulting Engineers in the summer of 2017.

This was an important rehabilitation project which engaged best practices for the removal and reconstruction of a structure while mitigating impact on surrounding vegetation and wildlife.

Project considerations included: removal and disposal of the existing dam structure in strategic phases, installation of metal railings and stop logs, and careful consideration of drainage, wetlands, and natural waterway channels.

Scope of Work

  • Dewatering
  • Installation of cofferdams
  • Cast-in-place dam structure
  • Precast bridge deck
  • Structural concrete repairs in water works
  • Granular backfill and restoration for Arnold Dam